Mayor Andre Dickens, Little Five Points leadership, and other officials are set to kick off a $3-million streets overhaul designed to make the fun-loving, eastside commercial district safer. Exactly what the project will entail is coming into sharper focus.
Atlanta Department of Transportation and Little Five Points Alliance officials have scheduled a Friday morning groundbreaking for the Euclid Avenue Safe Street project.
ATLDOT’s goal is to enhance pedestrian safety, beef up sidewalks and other infrastructure, and calm traffic through the funky, historic district. The scope calls for changes to start at Austin Avenue (where Inman Park’s stately homes transition to L5P businesses) and run up to Moreland Avenue, ending next to the opened-up Findley Plaza.
Specifically, according to L5P Alliance, improvements will include ADA-compliant crossings and curb ramps, widened sidewalks, more organized curbside parking and loading areas, safer pedestrian crossings, traffic-calming bulb-outs, fresh landscaping and “healthy, native trees” in all tree wells, better stormwater infrastructure, and a safer, redesigned intersection at Euclid and Austin avenues.
Another component will be “enhanced bike accommodations,” per ATLDOT.
Complete Streets alterations in the works where Euclid and Colquitt avenues meet in L5P. Atlanta Department of Transportation/Little Five Points Alliance
The broader goal is to slow traffic and boost walkability “while preserving the eclectic character and small-business energy that define Little Five Points,” per ATLDOT officials.
The project is made possible by a L5P Improvement District grant from the Atlanta Regional Commission's Livable Community Initiative that helped create the 2021 Little 5 Points Mobility Study, per district officials.
According to city officials, the streets remake will support the city’s Vision Zero initiative, which calls for eliminating traffic-related serious injuries and deaths by 2040 through improved transportation infrastructure and street redesign.
The project has officially been in the works since summer 2023, and designs wrapped this past spring. ATLDOT’s construction timeline calls for the project to be fully finished by early June next year.
Below, find a Before/After comparison of today’s Euclid Avenue in Little Five Points versus what’s planned.
But first, here’s a snapshot of planned changes, from above:
Street changes planned near Findley Plaza and Moreland Avenue, the eastern extent of the Euclid Avenue project. Atlanta Department of Transportation/Little Five Points Alliance/Kimley-Horn
Westernmost section of planned changes along Euclid Avenue. Atlanta Department of Transportation/Little Five Points Alliance/Kimley-Horn
Overview of full changes along Euclid Avenue in Inman Park and Little Five Points. Atlanta Department of Transportation/Little Five Points Alliance/Kimley-Horn
....